High Standard Mechanical Completion of Gas Fractionation Unit
in Fujian Refining & Ethylene Project
On August 31st , 2007, the EPC project of
Gas Fractionation Unit executed by LPEC was the first project mechanically
completed by high standard in Fujian refining & ethylene project.
The Unit engineering design was commenced on January 18th, 2007.
The construction of the unit was completed within five months which
is the shortest execution period for Gas Fractionation Units. LPEC's
Fujian Project Team is making all necessary preparations for the
successful commissioning and start-up of the unit.
|